Construction and renovation project Traffic control system and surveillance system on the Uttaraphimuk Elevated Tollway ("Smart Project")

7 Dec. 2020
899 views
INFORMATION
Location
Bangkok
Owner
Don Muang Tollway Public Company Limited
Project Cost
16,420,000 Baht
Project Period
15 October 2016 – 31 March 2018

Description

Uttaraphimuk Elevated Tollway or Don Muang Tollway. There are 2 sections; Din Daeng - Don Muang Section and National Memorial (Thailand) – Rangsit Section

Services Rendered

- Construction supervision and renovation of the main control room

 - Control of improvement control room

 - Control the installation of closed circuit television camera systems

 - Control the installation of the Matrix Sign (MS) sign on the Uttaraphimuk elevated Tollway

 - Control the installation of the over speed warning system

 - Control the screen line system installation

 - Control electrical installation work on the Over and Under Tollway and the Toll Plaza Building.

 - Control the installation of communication systems on the Uttaraphimuk Elevated Tollway