Consulting services for project management and construction supervision Southern Railway Construction Project (Double Track) Nakhon Pathom - Chumphon

19 Feb. 2021
566 views
INFORMATION
Location
Nakhon Pathom - Chumphon
Owner
State Railway of Thailand
Project Cost
1,092,000,000 Baht
Project Period
28 December 2017 – 28 December 2020

Project description

A double track railway construction project. The total distance is approximately 420 km. There are 60 stations, consisting of the construction of a ground-level railway and elevated railway bridges, bridges / underpasses at the intersection of the station building, and the installation of a 1 m. (Meter Gauge) trackwork system and installation of signal and telecommunication works.

Details of project

   1) Construction contract 6 contracts, consisting of:

       Civil work and rail system, 5 contracts (Nakhon Pathom - Nong Plalai section Nongplalai - Hua Hin Hua Hin - Prachuap Khiri Khan Prachuap Khiri Khan - Bang Saphan Noi And Bang Saphan Noi - Chumphon)

       And design work, procurement and installation of signaling and telecommunication systems for 1 contract (Nakhon Pathom - Chumphon range)

   2) Construction of new railway line with parallel to the old train line. Total distance is approximately 420 kilometers.

   3) 423 railway bridges

   4) 120 overpasses of railway bridges

   5) 37 U-Turn Bridges across the railway

   6) 12 underpass roads.

   7) Construction of the underpass in the box culvert

   8) Construction of a new train station

   9) Construction of a Centralized Traffic Control building (CTC)

  10) Construction of Container Yard (CY) station

  11) Design, supply and install Automatic Train Protection (ATP) signaling and telecommunication systems along the railway line