Project Description
The study area starts at Si Kai intersection, Road No. 13N (Km.6), Vientiane Capital to Baan Nam Sang km. 62 and from Mueang Nam Sang km. 62 and from the intersection of km. 35 (Ban Pakton) to Muang Sang Thong about 17 km and from Muang Sang Thong It converges to Road No. 11 (Ban Na Sa) 13 km, total length of about 92 km. Covering the Sanghom District and nearby areas in Nong Khai Province.
Service scope
- Study the economic suitability of the project
- Survey and map
- Geotechnical survey
- Survey and analysis of traffic and transportation
- Preliminary geometric design and assembly design, building work
- Preliminary design of bridges and drainage buildings
- Prepare tender documents detailing materials
- Construction cost estimate